Update on Further Road Works as part of the S2S works

28 Apr 2017

Below is an update from the CRA & CBA regarding additional road works as part of the S2S works.

 

As you will all be aware the James Larkin Road/Clontarf Road was closed in 3 sections on a 24-hour basis for a total of eight weeks from 10th October until 3rd December 2016 for resurfacing works. These closures had a significant impact on residents, businesses and commuters.  

As with any project of this size, the need for remedial works to fix defects was to be anticipated. Last Friday a letter was issued to the residents and businesses along the length of the S2S works advising them of further road closures. These closures will clearly also affect the many residents and businesses in the adjoining roads as well as commuters.  

Roadstone have met with us and provided the following details: 

The works are scheduled to commence on the 2nd of May and to be finished by the 12th of May 2017.  This timetable is, of course, weather dependent.  

The Clontarf Road will not be closed in full at any stage of these works.  

Works on the Clontarf Road will be undertaken using manual Stop/Go systems to facilitate traffic flow.

The end of Mt Prospect Ave, Dollymount Ave, Doyle’s Lane, Dollymount Park, Seafield Road East and Kincora Road where these roads join the Clontarf Road will be closed completely at times. Roadstone will have diversions in place during these closures. This element of the works is scheduled to commence on the 6th of May.  

The working hours will in the main be between 9 am and 9 pm.  

Pedestrian access will be maintained at all times.  

Roadstone will notify residents directly affected by the works with advance notice of exact dates and times of these works and will also provide relevant updates for loveclontarf.ie.